Overall health
0
/100At risk
Health dimensions
Schedule
78%
Resources
100%
Constraints
97%
Data quality
80%
Quick stats
Activities |
164
|
Completed |
0
|
Overdue |
80
|
Unresolved constraints |
2
|
Active conflicts |
0
|
Active alerts |
80
|
Health trend
Last 30 daysAI insights
Zone 'Building B' is heavily overbooked across the next 4 weeks
Area resource 'Building B' has capacity 1 but 144 activity assignments, with many activities scheduled in parallel in the same zone. Examples include 'Instalación de pisos de enchape - Nivel 2', 'Pintura 2da mano - Sótano 1', 'Puertas contraplacadas - Nivel 4', 'Tapajuntas - Nivel 1', and many others overlapping on the same dates. This indicates the zone plan is not controlling work fronts and will create trade stacking, access conflicts, and unreliable weekly execution.
High number of disconnected activities weakens schedule logic
The schedule has 164 activities, but 59 activities have no predecessors and 59 have no successors. This is a strong sign that large parts of the plan are not logically linked, so the model cannot reliably identify the true driving path to the project finish on 2026-08-22. Examples of unlinked start activities include 'Encimado de dinteles - Nivel 5', 'Pintura 2da mano - Sótano 1', 'Puertas cortafuego - Escaleras', and 'Impermeabilización de cisterna'. Examples of terminal activities with no successors include 'Baldosa drywall - Nivel 5', 'Pintura 2da mano - Nivel 3', and 'Sellos cortafuego - Escaleras'.
Activity durations are not credible for the scope shown
Nearly all listed activities have 'DurationDays' = 1 even when their calendar spans are much longer. For example, 'Empaste grueso - Nivel 4' runs from 2026-04-21 to 2026-05-19, 'Blanqueado de ambientes - Nivel 4' runs from 2026-04-19 to 2026-05-16, and 'Tapajuntas - Nivel 3' runs from 2026-05-27 to 2026-06-06, yet each is recorded as 1 day. This makes float, critical path, crew loading, and delay impact calculations unreliable.
Several predecessor-successor links run backward in time
Multiple finish-to-start relationships are date-inconsistent because the successor starts before its predecessor finishes. 'Pintura 2da mano - Sótano 1' has no predecessor, but its successor 'Limpieza fina - Sótano 1' starts on the same day the predecessor chain is still unresolved. More clearly, 'Vestidura derrames - Nivel 6' depends on '' and its successor 'Limpieza fina - Nivel 6' is scheduled from 2026-05-16 to 2026-05-21, which is before the predecessor activity starts on 2026-05-29. Another direct conflict is 'Impermeabilización de cisterna', finishing 2026-05-27, while its successor 'Anclajes y colocación de acero para viga de refuerzo' is scheduled on 2026-05-19, eight days earlier. These links make the network logically invalid.
125 activities have duration values that do not match their scheduled dates
The data summary reports 125 logical errors, and the listed activities show a recurring pattern where PlannedDuration is 1 day while the scheduled span is much longer. Examples include 'Empaste grueso - Nivel 4', scheduled from 2026-04-21 to 2026-05-19, and 'Instalación de pisos de enchape - Nivel 2', scheduled from 2026-05-08 to 2026-05-19. These mismatches make activity durations unreliable for sequencing, float, and critical path analysis.
Project finish is likely driven by unprotected late architectural finish chains
The latest dated activities in the dataset are concentrated in architectural finishing and extend close to the phase end, but several of them are weakly linked or not linked to a final milestone. Examples include 'Vestidura derrames - Nivel 5' (, ending 2026-06-17), 'Encimado de dinteles - Nivel 5' (, ending 2026-06-16), and 'Encofrado y vaciado de dinteles - Nivel 5' (, ending 2026-06-13). Because these late tasks are not consistently tied into a complete downstream chain, any slippage could remain hidden until it affects the project end date.
Material constraints are unresolved for two overdue activities
Both open constraints are in the Material category and are tied to activities that should already have started but are not completed. Constraint 'BUSCAR PROVEEDOR' affects activity 'Limpieza fina - Nivel 1', which was planned to start on 2026-05-05 and is now 20 days past start. Constraint 'COORDINAR COMPRA CON rICARDO cASTILLO' affects activity 'Anclajes y colocación de acero para viga de refuerzo', which was planned to start on 2026-05-19 and is now 6 days past start. With 2 of 2 open constraints blocking work within 7 and 14 days, the current material procurement process is an immediate execution risk.
Zone 'Building A' is also over capacity during May and early June
Area resource 'Building A' has capacity 1 but 20 activity assignments, including overlapping work such as 'Instalación de vidrios - Sótano 2', 'Esquinero en columnas - Sótano 2', 'Impermeabilización de cisterna', and 'Pintura en cuarto de materiales Torre E - Sótano 2'. With one area resource representing the whole building, concurrent assignments exceed the zone capacity and reduce the usefulness of area-based weekly control.
38 activities are disconnected from the schedule logic
38 of 164 activities, or 23.2%, are orphan activities with missing predecessor and/or successor links. Several listed activities appear disconnected despite being execution tasks in active finish work, such as 'Empaste grueso', 'Imprimación de muros', 'Pintura 2do mano', and 'Actividad 190', all of which have neither predecessors nor successors. This weakens sequence integrity and can hide true critical path behavior.
Week of 2026-05-18 is heavily loaded with 56 planned activities
The week starting 2026-05-18 contains 56 activities, the highest volume in the lookahead window. This concentration is significantly above the following weeks: 47 activities on 2026-05-25, 29 on 2026-06-01, 10 on 2026-06-08, and 3 on 2026-06-15. With no completion recorded yet, this week has a high risk of work stacking, trade interference, and short-term replanning pressure.
At least one predecessor-successor relationship is reversed in time
The activity 'Anclajes y colocación de acero para viga de refuerzo' has predecessor 'Impermeabilización de cisterna', but the successor is scheduled on 2026-05-19 while its predecessor runs from 2026-05-22 to 2026-05-27. This means the successor starts before the predecessor begins, which is impossible for a finish-to-start dependency and indicates either wrong dates or wrong logic.
Another dependency chain is scheduled out of sequence in Level 6 finishes
The activity 'Limpieza fina - Nivel 6' lists 'Vestidura derrames - Nivel 6' as its predecessor, but 'Limpieza fina - Nivel 6' is scheduled from 2026-05-16 to 2026-05-21 while its predecessor runs later, from 2026-05-29 to 2026-06-04. This reverses the intended sequence and can hide real completion risk for Level 6.
Week of 2026-05-25 remains overloaded with 47 planned activities
The week starting 2026-05-25 still carries 47 activities, creating a second consecutive high-volume week after the 56 activities planned for 2026-05-18. This back-to-back loading increases the chance that unfinished work from the prior week will spill over and disrupt planned starts such as 'Blanqueado de ambientes - Nivel 5', 'Tapajuntas - Nivel 3', and 'Pintura 2da mano - Nivel 3'.
Level 1 floor finish sequence contains a reversed dependency
The activity 'Terrazo en pisos - Nivel 1' depends on 'Limpieza fina - Sótano 1', but the predecessor ends on 2026-05-28 while the successor is scheduled earlier, from 2026-05-06 to 2026-05-22. This is not a valid finish-to-start sequence and suggests either the wrong predecessor was assigned or the dates were entered incorrectly.
Level 3 cleaning and finishing logic is internally inconsistent
The activity 'Empaste grueso - Nivel 3' depends on 'Limpieza fina - Nivel 2', but the successor is scheduled from 2026-05-15 to 2026-05-19 while the predecessor runs later, from 2026-05-23 to 2026-05-28. This is both a date reversal and a suspicious cross-level dependency, indicating likely copy-paste logic errors.
Several finish activities are likely to need materials but have none assigned
Multiple activities with clear material dependency have no material assignments. Examples include 'Instalación de vidrios - Sótano 2', 'Instalación de pisos de enchape - Nivel 2', 'Puertas contraplacadas - Nivel 4', 'Puertas cortafuego - Escaleras', 'Tapajuntas - Nivel 1', and 'Tapajuntas - Nivel 3'. These activities typically require procured items or consumables and may be delayed if materials are not defined and ordered in time.
Material constraint threatens week of 18 May activities
The week starting 2026-05-18 contains 56 planned activities, and 1 activity is not ready to start. Activity 'Anclajes y colocación de acero para viga de refuerzo' is scheduled for 2026-05-19 and has 1 unresolved material constraint. Because it is a one-day activity tied to reinforcement steel placement, any missing material on the planned date is likely to cause an immediate slip and disrupt follow-on structural work in the same area.
Several finish sequences start in the middle without enabling predecessors
Multiple activities appear to be mid-sequence finishing tasks but have no predecessors. Examples include 'Empaste grueso - Nivel 5', 'Fragua en enchapes - Nivel 2', 'Puertas contraplacadas - Nivel 1', and 'Vestidura derrames - Azotea'. These are normally preceded by substrate completion, wet-area readiness, frame installation, or prior finish layers. Without those links, the schedule allows work to start before the area is actually ready.
Several activities are scheduled to finish soon but show 0% progress
Multiple near-term activities ending between 2026-05-19 and 2026-05-21 still show 0% complete, including 'Instalación de vidrios - Sótano 2', 'Instalación de pisos de enchape - Nivel 2', 'Empaste grueso - Nivel 3', 'Pintura 2do mano', 'Fragua en enchapes - Nivel 2', 'Empaste fino - Nivel 4', 'Instalación de pisos de enchape - Nivel 3', and 'Terrazo en pisos - Nivel 2'. Even without constraint data, activities this close to finish with no recorded progress are at risk of slipping or reflecting outdated field updates.
Several terminal activities end without handover or follow-on logic
A number of activities that look like intermediate or near-final construction tasks have no successors, which means the schedule does not show what happens after they finish. Examples include 'Puertas cortafuego - Escaleras', 'Baldosa drywall - Nivel 4', 'Baldosa drywall - Nivel 3', and 'Colocación de topellantas - Sótano 1'. This breaks visibility of testing, punch list, cleaning, and turnover dependencies.
Immediate make-ready action needed for constrained material item
Only one constrained activity appears in the lookahead window, but it is scheduled at the front of the busiest week. Activity 'Anclajes y colocación de acero para viga de refuerzo' cannot be considered fully ready until its material constraint is cleared before 2026-05-19.
Long-duration activities with 0% progress may already be slipping inside the lookahead window
Some activities have unusually long durations for lookahead work but still show 0% progress, which is a weak readiness signal and may indicate stale planning or delayed starts. Examples include 'Empaste grueso - Nivel 4' from 2026-04-21 to 2026-05-19, 'Empaste fino - Nivel 4' from 2026-05-02 to 2026-05-20, 'Fragua en enchapes - Nivel 2' from 2026-05-08 to 2026-05-20, and 'Encimado de dinteles - Nivel 5' from 2026-06-05 to 2026-06-16. In lookahead planning, long open tasks with no progress reduce the reliability of weekly commitments.
Near-term activities cannot be checked for procurement readiness
Several activities start within the near-term window but have no material requirements recorded, so it is not possible to determine whether orders must be placed within the next 2 weeks. The earliest examples are 'Empaste grueso - Nivel 4' starting 2026-04-21, 'Instalación de pisos de enchape - Nivel 2' starting 2026-05-08, 'Pintura 2do mano' starting 2026-05-09, and 'Empaste grueso - Nivel 3' starting 2026-05-15). Without lead times or expected delivery dates, procurement timing is an unknown risk.
Both material constraints lack a clearly assigned responsible person
Neither constraint record includes an assigned responsible person. This creates follow-up risk because resolution ownership is unclear for 'BUSCAR PROVEEDOR' on 'Limpieza fina - Nivel 1' and 'COORDINAR COMPRA CON rICARDO cASTILLO' on 'Anclajes y colocación de acero para viga de refuerzo'. The second description names Ricardo Castillo, but the dataset does not confirm him as the accountable owner, so tracking remains incomplete.
Finishing sequences by level may be over-constrained and suitable for overlap
Several level-based finishing chains appear to be modeled as strict serial sequences even where partial-area handoffs could allow overlap. For example, Nivel 5 includes 'Fragua en enchapes - Nivel 5' → 'Instalación de contrazócalos de enchape - Nivel 5' → 'Instalación de vidrios - Nivel 5', while a separate chain includes 'Blanqueado de ambientes - Nivel 5' → 'Pintura 1ra mano en cto. técnico - Nivel 5'. If these tasks are area-based rather than full-floor completion gates, the current logic may be adding unnecessary waiting time.
Phase ARQUITECTURA has dates that do not align with its activities
Phase 'ARQUITECTURA' is scheduled from 2026-04-21 to 2026-08-03, but its earliest activity starts on 2026-04-19 and its latest activity ends on 2026-06-18. This means at least one activity starts before the phase start, and the phase finish extends well beyond the latest known activity. Such misalignment can distort phase-level reporting and milestone tracking.
Zone structure is incomplete because 'Building A - Floor 1' is unused
Area resource 'Building A - Floor 1' (ID: ) has capacity 1 and zero assignments, while the broader area resource 'Building A' (ID: ) carries 20 assignments. This suggests the project has started defining finer zone control but is not using it consistently. As a result, all work in Building A is being tracked at building level, reducing visibility of work-front conflicts and weakening lookahead control.
Placeholder activity names indicate poor schedule maturity
Several activities still use generic placeholder names such as 'Actividad 186', 'Actividad 189', 'Actividad 190', 'Actividad 191', 'Actividad 193', and 'Actividad 194'. Because their scope is undefined, their durations, logic, and impact cannot be validated.
Architecture phase starts after the project start date, leaving an unexplained gap
The project starts on 2026-04-09, but the ARQUITECTURA phase starts on 2026-04-21 while containing 160 of 164 activities. ESTRUCTURA spans the full project from 2026-04-09 to 2026-08-22 but only contains 4 activities. This may be intentional, but it creates a planning gap at the beginning of the project and suggests that enabling works, procurement, or early site activities may be missing from the schedule logic.
Several activities use placeholder names, reducing assignment reliability
Multiple scheduled activities in the next 4 weeks have non-descriptive names such as 'Actividad 186', 'Actividad 189', 'Actividad 190', 'Actividad 191', 'Actividad 193', and 'Actividad 194'. Although they have area assignments, these placeholder names make it difficult to verify whether the correct teams and zones are assigned and weaken weekly control.
Concrete crew assignment pattern should be reviewed for trade mismatch
Team 'Concrete crew' (ID: ) has only 3 assignments overall, and one of the visible near-term assignments is to 'Fragua en enchapes - Sótano 2' (Task ID: ) from 2026-06-05 to 2026-06-07. 'Fragua en enchapes' is a tile grouting activity, which does not align with a concrete trade. This may not be a capacity overload, but it is a resource coding issue that can distort team loading and hide real concrete crew demand.
Cost tracking is not set up for this project
All 164 of 164 activities have no cost data, and every listed activity shows a planned cost of 0. Because no activity-level cost information exists, cost quality and cost outlier analysis cannot be performed. This limits budget control and prevents meaningful earned value or cost trend checks.
Constraint and assignment data are complete, but material and field-readiness checks are missing
All 145 activities in the lookahead window show assignments present and zero unresolved constraints. This is positive, but it also means the current dataset does not identify whether materials, access, predecessor handoffs, permits, or inspections are actually ready. As a result, readiness can only be assessed from dates and progress, not from full make-ready status.
Several activities use generic placeholder names
At least 3 listed activities use non-descriptive names such as 'Actividad 186', 'Actividad 190', and 'Actividad 191'. Generic naming reduces schedule readability and makes it harder to validate logic, ownership, and progress updates.
Status consistency could not be validated from the available data
The dataset includes IsCompleted and IsCancelled flags, but it does not provide progress percentages or a detailed execution status field such as not started, in progress, or completed. Because of that, status inconsistency checks like 100% complete with an open status cannot be verified from the supplied data.
No circular dependencies were detected in the visible dependency graph
A review of the provided predecessor links did not reveal any explicit dependency loop of the form A → B → C → A among the activities included in the dataset excerpt. The schedule appears solvable from a graph perspective, although many links are missing or date-inconsistent.
Week of 2026-06-15 is underloaded with only 3 planned activities
The week starting 2026-06-15 has only 3 planned activities, far below the rest of the lookahead window. This suggests available capacity may be left unused if earlier work is completed as planned. It also indicates an opportunity to absorb work shifted from the overloaded weeks of 2026-05-18 and 2026-05-25.
Independent stair packages can be used to protect the finish date
The stair work packages contain several activities with weak or missing links, including 'Blanqueado en caja de escaleras', 'Pintura 1ra mano - Escaleras' in ESCALERA 2, and 'Enchape de pasos, contrapasos, descanso' in ESCALERA 2. Because these packages are partly disconnected from the main floor-finish chains, they may offer safe parallel execution opportunities if access and safety controls are available.
Area resource 'Building A - Floor 1' is unused
Area resource 'Building A - Floor 1' has capacity 1 and zero assignments, while the broader area resource 'Building A' is carrying 20 assignments. This suggests the zone structure exists but is not being used, which weakens lookahead planning and prevents work from being tracked by actual floor.
Generic activity names reduce lookahead control quality
At least three activities use non-descriptive names: 'Actividad 186', 'Actividad 190', and 'Actividad 191'. Generic naming makes it harder to verify readiness, assign accountability, and identify required materials or predecessor handoffs during weekly planning.
Concrete crew has very low utilisation and one assignment appears mismatched
Team resource 'Concrete crew' has only 3 assignments in the project. One visible assignment is to 'Fragua en enchapes - Sótano 2', which appears to be a finishing activity rather than concrete work. This suggests either low utilisation, incorrect team coding, or both.
Steel workers are largely idle and may be misassigned
Team resource 'Steel workers' has capacity 1 but only 1 assignment, to 'Lijado previo a empaste parapintura en cuarto de materiales Torre E - Sótano 2'. That activity name does not clearly match steel work, so the current assignment may be either a data error or a sign that the team is not being planned against actual steel-related tasks.
Engineering team is largely idle
Team resource 'Engineering team' has capacity 1 but only 1 assignment in the entire dataset. Compared with 169 total assignments in the project, this is a strong sign of underutilization or incomplete team assignment data.
No material requirements are defined in the project
The project contains 0 material requirements, 0 pending deliveries, and 0 delayed deliveries. At the same time, 20 activities are listed without assigned materials, including 'Instalación de pisos de enchape - Nivel 2', 'Pintura 2do mano', 'Puertas contraplacadas - Nivel 4', and 'Puertas cortafuego - Escaleras'. This prevents any reliable analysis of delivery risk, lead time conflicts, procurement timing, or logistics congestion.
No cost baseline has been distributed to project phases
The project budget is 12000000, but TotalPlannedCost is 0 and both phases, 'ESTRUCTURA' and 'ARQUITECTURA', have PlannedCost = 0. With 164 total activities across these phases, there is no phase-level cost baseline available to measure deviations, forecast overruns, or identify high-risk work packages.
Earned value metrics are not usable because no planned or actual costs are recorded
Cost Performance Index is reported as 1, but EarnedValue = 0, TotalPlannedCost = 0, and TotalActualCost = 0. This means CPI and SPI cannot be interpreted as indicators of cost or schedule efficiency. In addition, completed activities are 0 of 4 in 'ESTRUCTURA' and 0 of 160 in 'ARQUITECTURA', so there is no earned value basis for performance analysis.
Current cost data coverage is too limited to detect burn rate or overrun trends
ActivitiesWithCostData is 0, ActivitiesWithOverruns is empty, and ActualCost is 0 against a project budget of 12000000. Because no activity, work package, or phase has recorded actual spending, it is not possible to identify accelerating cost growth, abnormal unit costs, or phases spending faster than planned.